Bauskas apvadceļš

Current project status: Development of PPP procurement documentation

Project contact persons: Kristīne Apsalone VSIA “Latvian State Roads”, kristine.apsalone@lvceli.lv  

Project website

  • Project goal: Construction of the Bauska bypass.
  • Public partner: Ministry of Transport, VSIA “Latvian State Roads”.
  • PPP model: Design, build, finance, maintain (DBFM).
  • CAPEX: 114.9 MEUR excluding VAT (in 2022 prices).
  • Project accounting: Off-balance sheet project.
  • Term: 23 years (3 years construction + 20 years maintenance).
  • PPP contract start date: Provisionally June 2028.
  • Construction work completed, object available: Provisionally 2030/2031.
  • PPP contract end date: Provisionally 2050/2051.
  • PPP contract price: Approximately EUR 263,306,000 - 290,726,000* (excluding VAT). *Due to the impact and proximity of the Rail Baltica project, technical solutions may change, potentially affecting the project's capital investments.
  • Availability payment per year: Provisionally 13.1-14.5 MEUR.
  • PPP procurement:  Competitive procedure with negotiations in two stages (qualification, submission of bids). 

Draft legislation 23-TA-2023

Abstract 

  • FEA agreed: 22.12.2022. (CFLA); 30.12.2022. (FM). 
  • FEA procurement: announced on 17.02.2022 - EIS

02.06.2022. contract signed, FEA developer SIA “Deloitte Latvia”

Informative report "On financing possibilities for the reconstruction of the section of the main national road A7 Riga–Bauska–Lithuanian border from the Ķekava bypass to Bauska".