Selijas poligons

Current project status: PPP FEA development

Project contact person: 

Ģirts Zālītis, VAS “State Real Estate”, girts.zalitis@vni.lv  

Dace Barkāne, Ministry of Defence, dace.barkane@mod.gov.lv 

Project website

  • Project goal: Construction of residential, administrative, and traffic infrastructure of the “Sēlija” military base in Nīkrāce.
  • Public partner: Ministry of Defence, VAS “State Real Estate”.
  • PPP model: Design, build, finance, maintain (DBFM).
  • CAPEX: 403 MEUR excluding VAT (in 2025 prices).
  • Project accounting: Off-balance sheet project.
  • Deadline: To be specified in the FEA.
  • PPP contract start date: To be specified in the FEA.
  • Construction work completed, object available: Provisionally 2030.
  • PPP contract end date: Provisionally 2060.
  • PPP contract price: Will be provisionally determined from the FEA.
  • Availability payment per year: Will be provisionally deduced from the FEA.
  • ​​​​​​PPP procurement: Will be provisionally concluded from the FEA.
  • FEA saskaņoti: Provizoriski 2026.gada novembris.
  • FEA izstrāde: 09.10.2025. sadarbībā ar EIB. 09.10.2025. starp Aizsardzības ministriju un VNĪ ir noslēgts deleģēšanas līgums.
  • Lēmums par FEA izstrādi: FEA sagatavošanas lēmumi 26.09.2025. (Aizsardzības ministrija).
  • MK ziņojums par PPP ietvara īstenošanu aizsardzības infrastruktūras būvniecībā: MK sēdes protokollēmuma projekts 23.09.2025.
  • MK ziņojums par prioritāro projektu identificēšanu: MK sēdes protokollēmuma projekts 13.05.2025.
  • MK rīkojums par iepirkuma procedūras uzsākšanu: Provizoriski būs secināms pēc FEA izstrādes.
  • Finanšu un juridisko konsultāciju iepirkums PPP līguma vadībai: Provizoriski būs secināms pēc FEA izstrādes.
  • Iepirkuma dokumentācijas izstrāde un saskaņošana ar CFLA: Provizoriski būs secināma pēc FEA izstrādes.
  • FEA agreed: Provisionally November 2026.
  • Development of the FEA: 09.10.2025. in cooperation with the EIB. on 09.10.2025. a delegation agreement has been concluded between the Ministry of Defence and the VNĪ.
  • Decision on the development of the FEA: FEA preparation decisions 26.09.2025. (Ministry of Defence).
  • Cabinet report on the implementation of the PPP framework in the construction of defense infrastructure: draft protocol decision of the Cabinet meeting (23.09.2025).
  • Cabinet report on the identification of priority projects: draft protocol decision of the Cabinet meeting (13.05.2025).
  • Cabinet order on the initiation of the procurement procedure: Preliminary conclusions will be drawn after the development of the FEA.
  • Procurement of financial and legal advice for the management of the PPP contract: Will be provisionally concluded after the development of the FEA.
  • Development and coordination of procurement documentation with CFLA: Will be provisionally concluded after the development of the FEA.