Rīgas lidostas komercplatību apsaimniekošana

Current project status: Concession procedure

Project contact: Vaiva Kirvelaite,  V.Kirvelaite@riga-airport.com

  • Project goal: Development of commercial space at Riga Airport, selection of a commercial space manager.
  • Public partner: Riga Airport.
  • PPP model: Design, build, finance, maintain (DBFM).
  • CAPEX: 15.6 MEUR excluding VAT (in 2025 prices).
  • Project accounting: Off-balance sheet project.
  • Term: 12 years (including 4 years of improvement works).
  • Concession procurement documentation agreed: 30.06.2025. (1st round), 17.09.2025. (2nd round).
  • Concession procurement announced: 03.07.2025. IUB Announcements.
  • FEA agreed: 22.05.2025 (CFLA), 12.06.2025 (FM).
  • FEA development service procurement: contract concluded on 21.08.2023, winner “PricewaterhouseCoopers SIA” - EIS.
  • Decision on the development of FEA: FEA preparation decisions 20.01.2020. (Riga Airport).